Detention Basin Computation in MSMA (2000)

 

 

Sample Data

Site Detail

Location : Federal Territory, Kuala Lumpur
Area : 10 Ha
2P24 : 100mm
Tc Pre : 30min
Tc Post  : 15min
Pre site condition : Urban Area, Park Lawns and Meadows
Post site condition : Urban Area, SemiD Houses on Bare Earth

 

Outlet Selected

Type : Orifice
Numbers : 1
Cd : 0.6
Do : 1 m
Invert Level : 0 m

 

Detention Basin Design

ARI for Pre : 5 year, 50 year and 100 year
ARI for Post : 5 year, 50 year and 100 year
Td Pre : 10min, 20min, 30min
Td Post : 10min, 20min, 30min
Basin Area : 6000 m2, 7000 m2, 8000 m2, 9000 m2, 10000 m2, 11000 m2
Contour Interval Depth : 0.15 m
Max Depth : 3.0 m
Invert Level : 0 m
Free Board : 0.3 m
No of contour lines : 6
Basin routing time step : 5 min
Factor to Tc : 4

 

Back : Case Study 1                                              Next : MSMAware Computation


 

 

Print This Page Print This Page

Leave a Reply

Your email address will not be published. Required fields are marked *

*
*
Website