General data:

 

Location                      : Klinik Bukit Bendera, Pulau Pinang

Area                            : 30 Hectare

Time, Tc                      : 30 Minutes

²P24                             : 150 mm

Site Condition              : a) SemiD Houses

b) Park

c) Commercial

 

Step 1: Start MSMAware and click “Rational Method”. Make sure to compute the storm result before run the rational method. Follow steps shown in chapter 1 for design storm.

 

For steps 2 until 6, please follow the steps shown in case study 1 for Kuala Lumpur

 

 

Back : Case Study 2 Pulau Pinang                      Next : Manual Calculation

 